Different Designs of Sulabh Shauchalayas And Costs
Model No. 1
Substructure : Mud platform plastered in cement mortar 1:4,
cement plastered pan, cement trap and brick
plastered foot rests. Pit lining – Tar drum, Pit cover –
Compacted soil over thatch and logs.
Superstructure : Jute all round the latrine on bamboo frame 1800 mm high and curtain made of jute for a door .
Cost : Substructure : 5 users with 2 years capacity pits Rs. 1100
Superstructure : Rs. 500
Unskilled labour to be provided by house owner
Model No. 2
Substructure : Mud platform plastered in cement
mortar 1:4, cement plastered pan, cement trap and
brick plastered foot rests. Pit lining – Brick work 75
mm in cement mortar 1:6, Pit cover – Compacted
soil over thatch and logs.
Superstructure : Palm matting all round the
latrine on bamboo frame 1800 mm high and jute
purdah on door opening, painting on matting.
Cost : Substructure : 5 users with 2 years capacity pits Rs. 1900
Superstructure : Rs. 600
Unskilled labour to be provided by house owner
Model No. 3
Substructure : Dry brick ballast in foundation, brick work in mud
mortar, flooring of 12 mm thick 1:4 cement plaster
over 75 mm dry brick ballast, cement mosaic pan,
cement trap and brick plastered foot rests. Pit lining – Brick work 75 mm in cement mortar 1:6, Pit cover –
50 mm thick R.C.C. 1:2:4.
Superstructure: Thatch wall with thatch roof on bamboo frame and
jute purdah on door opening 1800 mm high.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 1900
- 5 users with 3 years capacity pits Rs. 2200
- 10 users with 2 years capacity pits Rs. 2600
Superstructure : Rs. 750
Model No. 4
Substructure : Dry brick ballast in foundation, brick work in cement
mortar, flooring of 12 mm thick 1:4 cement plaster
over 75 mm dry brick ballast, cement mosaic pan,
cement trap and brick plastered foot rests. Pit lining – Brick work 115 mm in cement mortar 1:6, Pit cover – 75 mm thick R.C.C. 1:2:4.
Superstructure : 115 mm thick brick work in 1:6 cement mortar 1500
mm high and jute purdah on door opening 1800 mm
high.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 4600
- 5 users with 3 years capacity pits Rs. 5700
- 10 users with 2 years capacity pits Rs. 6400
Superstructure: Rs. 3000
Model No. 5 (G-Shape)
Substructure : Dry brick ballast in foundation, brick work in cement
mortar, flooring of 12 mm thick cement plaster over
75 mm dry brick ballast, mosaic pan, cement trap,
brick plastered footrest, Pit lining – brick work 115
mm in cement mortar 1:6, Pit cover – 75 mm thick
R.C.C. 1:2:4.
Superstructure : 115 mm thick brick work in 1:6 cement mortar 1500
mm high. It is G-Shape no door required.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 5200
- 5 users with 3 years capacity pits Rs. 6350
- 10 users with 2 years capacity pits Rs. 7000
Superstructure: Rs. 2100
Model No. 6 (Circular)
Substructure :Dry brick ballast in foundation, brick work in cement mortar, flooring of 12 mm thick cement plaster over
75 mm dry brick ballast, mosaic pan, cement trap,
brick plastered footrest, Pit lining – brick work 115
mm in cement mortar 1:6, Pit cover – 75 mm thick
R.C.C. 1:2:4.
Superstructure :Circular 115 mm thick brick work in 1:6 cement
mortar 1500 high. It is like G-Shape no door
required.
Cost :
Substructure
- 5 users with 2 years capacity pits Rs. 5200
- 5 users with 3 years capacity pits Rs. 6350
- 10 users with 2 years capacity pits Rs. 7000
Superstructure : Rs. 2700
Model No. 7
Substructure : Dry brick ballast in foundation, brick
work in 1:6 cement mortar, flooring of 1:4 cement
plaster over 75 mm dry brick ballast, cement mosaic
pan, cement trap and brick plastered foot rests. Pit
lining – Brick work 115 mm in cement mortar 1:6, Pit
cover – 50 mm thick R.C.C. 1:2:4.
Superstructure : 115 mm thick 1500 mm high brick wall in cement mortar 1:6 (G-shape)
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 5250
- 5 users with 3 years capacity pits Rs. 6400
- 10 users with 2 years capacity pits Rs. 7050
- 10 users with 3 years capacity pits
(Pit cover 75 mm thick) Rs. 8350
Superstructure: Rs. 2100
Model No. 8
Substructure : Cement concrete 1:6:12 in foundation, brick work in
1:6 cement mortar, flooring of 1:4 cement plaster
over 75 mm dry brick ballast, cement mosaic pan,
cement trap and brick plastered foot rests. Pit lining – Brick work 75 mm in cement mortar 1:6, Pit cover –
50 mm thick R.C.C. 1:2:4.
Superstructure : 115 mm thick brick wall in 1:6 cement mortar, A.C.
sheet roofing, holes in brick work for ventilation and
jute purdah 1800 mm high. Inside white wash and
outside colour wash.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 4700
- 5 users with 3 years capacity pits Rs. 5850
- 10 users with 2 years capacity pits Rs. 6500
- 10 users with 3 years capacity pits
(Pit cover 75 mm thick) Rs. 7800
Superstructure: Rs. 3450
Model No. 9
Substructure : Cement concrete 1:6:12 in foundation, brick work in
1:6 cement mortar, flooring of 1:4 cement plaster
over 75 mm dry brick ballast, fibre glass pan, HDPE
trap and ceramic foot rests. Pit lining – Brick work
115 mm in cement mortar 1:6, Pit cover – 50 mm
thick R.C.C. 1:2:4.
Superstructure : 115 mm thick brick wall in 1:6 cement mortar 1500 mm high, 600 mm high dado in
cement mortar 1:4, both sides plastered in 1:6
cement mortar and jute purdah on door opening
1800 mm high.
Cost : Substructure
- 5 users with 3 years capacity pits Rs. 5700
- 10 users with 3 years capacity pits Rs. 7000
Superstructure : Rs. 3200
Model No. 10
Substructure : Cement concrete 1:4:8 in foundation, brick work in
1:6 cement mortar, C.C. 1:2:4 flooring over 75 mm
C.C. 1:6:12, fibre glass pan, HDPE trap and ceramic foot rests. Pit lining – Brick work 115 mm in 1:6
cement mortar, Pit cover – 50 mm thick R.C.C. 1:2:4.
Superstructure : 115 mm thick brick work in 1:6
cement mortar, 600 mm high dado in cement mortar
1:4, 50 mm thick R.C.C. roof, holes in brick work for
ventilation and country wood door 1500 mm high.
Inside white wash and outside colour wash.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 4700
- 5 users with 3 years capacity pits Rs. 5850
- 10 users with 3 years capacity pits
(Pit cover 75 mm thick) Rs. 7800
Superstructure : Rs. 4450
Model No. 11
Substructure : Cement concrete 1:4:8 in
foundation, brick work in 1:6 cement mortar, C.C.
1:2:4 flooring over 75 mm C.C. 1:6:12, fibre glass pan, HDPE trap and ceramic foot rests. Pit lining –
Brick work 115 mm in 1:6 cement mortar
(Rectangular pit divided by a partition wall in two
chambers), partition wall plastered on both sides in
cement mortar 1:6, Pit cover – 50 mm thick R.C.C.
1:2:4.
Superstructure : 115 mm thick brick work in 1:6
cement mortar, outside plastered, 600 mm high
dado in cement mortar 1:4 holes in brick work for
ventilation, R.C.C. roof 50 mm thick and country
wood door 1500 mm high. Inside white wash and
outside colour wash.
Cost : Substructure
- 5 users with 2 years capacity pits Rs. 5000
- 5 users with 3 years capacity pits Rs. 6200
- 10 users with 2 years capacity pits
(Pit cover 75 mm thick) Rs. 8200
- 10 users with 3 years capacity pits
(Pit cover 75 mm thick) Rs. 9500
Superstructure : Rs. 4450
Model No. 12
Substructure : Cement concrete 1:4:8 in foundation, brick work in
1:6 cement mortar, Ceramic tiles flooring over 25
mm thick C.C. 1:2:4 base on 75 mm C.C. 1:4:8,
Ceramic European Pan, Porcelain Trap. Pit lining –
Brick work 223 mm in cement mortar 1:6, Pit cover –
115 mm thick R.C.C. 1:2:4 wash basin with mirror.
Superstructure : 225 mm thick brick work in 1:6
cement mortar, plaster on both sides, 900 mm high
while glazed tiles dado, wooden ventilator, 75 mm
thick R.C.C. roof and Aluminium panelled door with
Aluminium frame 2100 mm high. Inside ceramic
tiles and outside colour wash.
Cost : Substructure
10 users with 10 years capacity pits Rs. 26800
Superstructure : Rs. 32000
|